bigjohnsd
2021 BMW R1250GSA
Chief Joseph Scenic Highway, Paint Creek Canyon & Two Dot Sections
Project Number: STP 35.58-DR51574 & SCP-TC 33.20 1507036_
WYDOT Contact: Todd Frost, phone: 307-587-2220, email: [email protected]
Contractor: Oftedal Construction, Inc., Miles City, MT, 406-232-5911
Scheduled Completion Date: 2017-Jun-30
Grading, milling plant mix, placing crushed base and bituminous pavement surfacing, chip seal, bridge deck repair and miscellaneous work on 13.32 miles of WYO 296 begiining at RM 46.20 on Chief Joseph Scenic Highway. Expect up to 20-minute delays with stopped conditions.
Road
Milepost(s)
Surface
Delays and Scheduled Closures
WY296
33.2 to 46.2
Paved
20 minute delays with stopped conditions
Last Updated: 2016-06-15 13:39:58.837
Project Number: STP 35.58-DR51574 & SCP-TC 33.20 1507036_
WYDOT Contact: Todd Frost, phone: 307-587-2220, email: [email protected]
Contractor: Oftedal Construction, Inc., Miles City, MT, 406-232-5911
Scheduled Completion Date: 2017-Jun-30
Grading, milling plant mix, placing crushed base and bituminous pavement surfacing, chip seal, bridge deck repair and miscellaneous work on 13.32 miles of WYO 296 begiining at RM 46.20 on Chief Joseph Scenic Highway. Expect up to 20-minute delays with stopped conditions.
Road
Milepost(s)
Surface
Delays and Scheduled Closures
WY296
33.2 to 46.2
Paved
20 minute delays with stopped conditions
Last Updated: 2016-06-15 13:39:58.837